Legacy modernisationbad news for the people this stream is for

A revised business case for the NS&I programme to replace its legacy technology and data estate puts the ten-year cost at £3.84bn, up from £2.85bn, with completion moving from March 2028 to July 2029. Interim chief executive Sir Jim Harra told the Treasury Committee that NS&I fundamentally underestimated the complexity and had not fully grasped what managing several suppliers and their dependencies would need. The case includes contingency for optimism bias.